Clarification of

  • Technical data and requirements
  • Boundary conditions
  • System interfacing

Calculation of the relevant application data

  • Stationary, dynamic, regenerative power
  • Speeds

Gear unit selection

Determining

  • Gear unit design, gear unit size, gear unit ratio

Check for gear unit utilization (Mamax ≥ Ma(t))

Motor selection

  • Convert torque and speed for the motor shaft
  • Define the motor

Check

  • Max. torque which can occur Mmax < 1.5 × MN
  • Required motor speed < nN
  • Thermal load with regard for the setting range and cyclic duration factor

Selection of theMOVITRAC® LTP-B frequency inverter

  • Motor/inverter assignment
  • Continuous power, peak power
  • Installation conditions

Selection of the braking resistor

  • On the basis of the calculated regenerative power and the cyclic duration factor

Options selection

  • External display, cable sets, etc.

Check whether all requirements are met.