Gateways, communication modules, and cable routing

Before switching on the voltage, first install all components, see chapter Automatic configuration after delivery.

Proceed as follows:

  1. Remove the (signal) terminal cover and install it offset downwards.
  2. Install the gateway [2] on the front of the inverter and tighten the retaining screw [4].
  3. Mount the cable clip [3] on the cover [1] as cable routing for the network cables.
    • The gateway has been installed.
  4. Connect the network cables.
    • For fieldbuses: No sequence X40/X41
    • For EtherCAT®/SBusPLUS: IN X30 and OUT X30
  5. To secure the network cables [4], use the cable clip [3].
  6. Install the communication module [1] on the front of the inverter and tighten the retaining screw [2].
  7. Connect the gateway to the communication modules with the supplied ribbon cable [6] and route it as follows:
  8. Reinstall the transparent front cover [7] for all communication modules.

INFORMATION

The gateway network must be set up without any gaps. A two-row or detached setup is not permitted.