Working brake – BE.. brake
If the result of the respective tests in the project planning procedure is negative, the following table describes the possible project planning measures for an alternative drive.
Checks | Formula | Possible measures |
|---|---|---|
Is the braking torque sufficient? | 1.1 |
|
Is the permitted switching frequency sufficient? | 1.6 |
|
Is the vertical/horizontal braking work sufficient? | 1.8 |
|
Is the brake service life sufficient? | 1.11 |
|
Final drive check: Calculating the drive considering the selected components and their characteristic values (such as inertia) For detailed configuration criteria and procedures, refer to the SEW‑EURODRIVE project planning guidelines. | – |
|
Is the braking load of the gear unit (torque) permitted? | 1.14 |
|
Is the braking load of the gear unit (overhung load) permitted? | 1.16 |
|
Is braking distance/stopping distance sufficient? | 1.20 1.21 |
|
Is the deceleration permitted? | 1.23 |
|