Step 1
- Disconnect the connection between MDP92A or MDE90A and the energy storage unit, e.g. via the DC contactors using the controller.
- Disconnect the system from the AC grid. Make sure that you disconnect all relevant connections if there are several AC connections.
- Make sure that all the connections that are now opened cannot be reconnected during service work.
- Make sure that the supply unit is de-energized at all poles using a suitable measuring instrument. Perform the measurements at all locations shown in the overview on the inside of the door.
- For the low-temperature variant and high-temperature variant, you also need to ensure that all poles are de-energized at terminal X10.