Process sequence and signal states
No. | Procedure | PD | Signal states |
---|---|---|---|
[1] General enable |
| PO 1:0 (axes) |
|
| PO 1:1 (axes) |
| |
| PO 1:13 (axes) |
| |
[2] | Selection of the "Transfer to stock" operating mode | PO 6 (group) |
|
[3] | Start/stop of operating mode | PO 1:7 (group) |
|
Transfer to stock in progress | PI 1:11 (group) |
| |
[3] to [4] | The belt starts transporting the box in the direction of the synchronous point. | ||
The telescope waits because its synchronization distance is shorter than the distance of the box to the synchronous point. | |||
[4] to [5] | The belt transports the box in the direction of the synchronous point. | ||
The telescope starts synchronization. | |||
[5] | The belt and telescope are in synchronous operation. | ||
[5] to [6] | The box is transferred from the belt to the telescope. | ||
[6] to [7] | The belt starts the stopping process and has transferred the box completely to the telescope. | ||
The telescope positions the box further to the target position in the warehouse. | |||
[7] | The belt is stopped. | ||
[7] to [8] | The telescope continues with positioning. | ||
[8] | Transfer to stock completed | PI 1:7 (group) |
|
Transfer to stock no longer performed | PI 1:11 (group) |
|