Reinstallation
- Remove the cover of the new discharge connection unit.
- Restore the electrical connections.
UZ+ cable | CE: F10:2 UL: F10.1 |
UZ- cable | CE: F10:8 UL: F10.3 |
PE | PE busbar |
- Establish a mechanical cable relief by tightening the cable glands.
- Mount and screw the discharge connection unit into the control cabinet at the top position of the system rail.
The screw for the PE connection is equipped with a serrated lock washer. - Mount the housing cover on the discharge connection unit.
- Connect the short-circuit connector to X2 to short-circuit the energy storage unit.
- Set fuse F10 to "On". This step is omitted for the UL variant.
- Remove the short-circuit jumper from the energy storage unit.
- Reinsert the protective grid and screw it in place.